How long does it take to complete an agrivoltaic project?

The development required for an agrivoltaic project is the same as for a conventional solar project. It takes around 5 years from the signing of the Land Agreements (between the landowner and the energy company) to the commissioning of the park. This time frame includes environmental impact studies for the four seasons (1 year), the preliminary agricultural study, the time required for governmental approval (1 year) and the time required for connection (2 to 3 years).